When the Banes General Contractors’ One Year Warranty was due to expire, Huitt-Zollars monitored the contractor to assure they corrected any final remaining warranty issues. Due to extensive Owner initiated design changes late in construction, the design team was required to move fast on changes, obtain approval from the City and upon approval deliver the design changes to Huitt-Zollars to review and forward to the General Contractor for pricing. Although the project had many challenges, the solid construction management practices, determination and proactive effort by the Huitt-Zollars Construction Management Team achieved final success and final completion of the project.
Sun Metro Lift Operations and Maintenance Facility
El Paso
Client
Sun Metro Transportation Agency